Nordex-Kürekdağı Wind Turbine Transportation and Installation Project
Starting Date: 08/08/2017
Ending Date: 11/15/2017
Equipments Used in the Project: LG1750 - LTM1750 - FAUN220 - LTM1200 - AC200 ; in addition, a total of 18 units, 4 to 8 axles, were used for the transports, with extended trailer
Project Details: 10 * NORDEX N117 TS106 Turbine transport and installation (Towers transported from Çimtaş, impellers from TPI and turbine components from Gemlik Port to construction yard. During transport, due to the inadequacy of the itinerary, Towers and Impellers transported from Bandırma Port to Mendirek that was constructed dedicatedly in Yalova Fıstıklı with RORO)