Revolutionary new marine solution meets water
Start Date: 19.01.2021
Date of Completion: 21.01.2021
Equipment used in the project: 2 files, 24 axle-lines of conventional hydraulic trailers and 2 files 24 axle-lines of self propelled modular trailers (SPMT) and 2 units of 600 tons capacity Terex Demag CC 2800 crawler cranes
Project Description: Revolutionary Fast Crew Supplier (FCS) 7011 was successfully launched into the water at Damen Shipyards Antalya. Hareket used a combination of 2 files, 24 axle-lines of conventional hydraulic trailers and 2 files 24 axle-lines of self propelled modular trailers (SPMT) to move 410t weighing FCS 7011 out of the building shed where she was built. Two crawler cranes with 600t lifting capacity tandem lifted 70 meters long aluminum vessel and dip her gently into the water. FCS was delivered safely on schedule.