Load Out operations of two 650T Jackets
Start Date: DP-1 23.02.2021 / DP-2 13.04.2021
Date of Completion: DP-1 24.02.2021 / DP-2 14.04.2021
Equipment used in the project: DP-1, 40 axle lines of self propelled modular trailers (SPMT) with 3 power pack units and DP-2, by using 56 axle lines of SPMT with 4 power pack units
Project Description: Hareket has successfully executed load out operations of 650T DP-1 & 650T DP2 Jackets with dimensions of 31 x 27 x 23 meters by using 40 axle lines of self propelled modular trailers (SPMT) with 3 power pack units and 52 x 28 x 23 meters by using 56 axle lines of SPMT with 4 power pack units within the scope of Northern Marmara Natural Gas Storage Extension (Phase III) Project.